A technical specification turns design intent into a file that can be quoted, fabricated and accepted. It is not a substitute for drawings; it is the summary of drawings, acceptance criteria and responsibility boundaries. The content depends on the project size, the local code and the acceptance requirements, so there is no single template, but every spec should cover design loads, materials, coatings, tolerances, acceptance and supplier duties. ZhongSai has built steel structures for 20 years and focused on exports for 15, and coordinates engineering and detailing on the buildings we fabricate.

This guide lists the sections a buyer can put into the spec so the fabricator quotes the same building the designer intended.

Engineer reviewing a steel building technical specification and drawings (illustrative concept image)

Part 1: What a specification is in the procurement flow

DocumentWhat it doesWhat it is not
DrawingsDefine geometry and connectionsDo not state acceptance criteria
Technical specificationState loads, materials, coatings, tolerances, acceptanceNot a replacement for drawings
RFQ / inquiryAsk for price and lead timeNot a design document
Supply contractFix scope, price, lead time, warrantyBuilt on the spec

Part 2: Sections a steel building spec should cover

  • Design basis: the design code, the site, the loads (wind, snow, seismic, crane, equipment), the building use and the required design life
  • Materials: steel grade, bolts, welding consumables, and whether standards like ASTM or EN are required
  • Coatings and fire protection: surface preparation, coating system, dry film thickness and fire rating where required
  • Fabrication: tolerances, weld categories, inspection and testing requirements
  • Erection: responsibility for installation, sequence and site requirements
  • Acceptance: what will be checked before shipment and at handover, and who approves

Specification documents, drawings and tools on an engineer's desk (illustrative concept image)

Part 3: Responsibility boundary

StageBuyer / designerSupplier (ZhongSai)
DesignEngage the registered engineer, fix loads and local codeEngineering coordination and detailing per the spec
MaterialsState grades and standardsFabrication, QC, marking and packing
ApprovalApprove drawings and shop detailsProvide fabrication and detail drawings for review
SitePermits, foundations, civil works, local labourInstallation technical guidance and export coordination

Steel sections and primed components for a fabricated building (illustrative concept image)

Part 4: Specification vs quotation

AspectGood specificationVague inquiry
Design codeNamed (e.g. AISC, EN 1993, GB 50017)Not stated
LoadsWind/snow/crane/equipment loads given“Standard design”
MaterialsGrade and standard named“Good quality steel”
CoatingsSystem and DFT stated“Anti-corrosion”
AcceptanceInspection points and standards listedNot defined
ResultComparable quotes, fewer claimsMisquotes and disputes

Part 5: Checklist before you send the spec

  • Design code and load conditions written down
  • Steel grade, bolts and welding consumables named
  • Coating system and dry film thickness stated
  • Fire rating or fire protection requirement defined
  • Tolerance and inspection requirements listed
  • Erection responsibility and site conditions described
  • Approval workflow for shop drawings agreed

Engineer measuring a fabricated section during dimensional acceptance (illustrative concept image)

Engineers cross-checking drawings against the specification (illustrative concept image)

FAQ

What is a technical specification for a steel building?

A document that states the design basis, materials, coatings, tolerances, inspection and acceptance for the building, so the fabricator builds what the designer intended.

What information does a steel fabricator need?

Drawings plus a spec with the design code, loads, steel grade, coating system, tolerances and acceptance criteria.

Which standards should the spec reference?

The code that applies at the project site, for example AISC, EN 1993 or GB 50017; the spec should name it rather than saying “standard design”.

Who writes the specification?

Usually the buyer’s designer or registered engineer. ZhongSai can coordinate and review the detailing, but the design basis comes from the project’s engineer.

What happens if the spec and the drawings conflict?

The conflict should be resolved in writing before fabrication, usually by the buyer’s engineer, because it changes scope and cost.

Does the spec affect the price?

Yes. Named grades, coating systems and inspection requirements make quotes comparable and reduce claims after shipment.

Do you fabricate to the buyer’s specification?

ZhongSai fabricates to the agreed spec and drawings, and coordinates detailing, QC, marking, packing and export per the supply contract.

What should I do if I have drawings but no specification?

Send the drawings together with the design loads and code; ZhongSai can help list the open points before quoting.